Campus Details

  • 267 acres
  • 415,000 sf
  • 2,030 parking spaces

Project Plans

LSC-Kingwood Project Phasing

Phase 1: Feb 2015 - Dec 2016

  1. Student Services expansion: 10,000 sf
  2. LSC-Process Technology Center (Oil/Gas/Water): 50,000 sf

Phase 2: July 2016 - June 2018

  1. New Healthcare Instructional Building: 60,000 sf
  2. Increase surface parking: 550 spaces

Phase 3: Jan 2018 - Dec 2019

  1. Renovations to existing facilities: 28,000 sf
  2. Traffic infrastructure
  3. Multiple facility condition assessment projects