2014 Bond LSC-University Park
We are currently updating the GO Bond Projects web pages. More information will be available and the web pages updated soon.
Campus Details
- 72 acres
- 1,350,000 sf
- 4,600 parking spaces
Project Plans
LSC-University Park Project Phasing
Phase 1: Feb 2015 - Dec 2016
- New Instructional Science Building: 50,000 sf
- Workforce Certification Assessment Center (build out floor): 25,000 sf
- Multiple bond funded renovations: 55,000 sf
Phase 2: July 2016 - June 2018
- New Instructional Arts Building: 40,000 sf
- Increase surface parking: 170 spaces
Phase 3: Jan 2018 - Dec 2019
- Multiple facility condition assessment project