2014 Bond LSC-University Park

We are currently updating the GO Bond Projects web pages. More information will be available and the web pages updated soon.

Campus Details

  • 72 acres
  • 1,350,000 sf
  • 4,600 parking spaces

Project Plans

LSC-University Park Project Phasing

Phase 1: Feb 2015 - Dec 2016

  1. New Instructional Science Building: 50,000 sf
  2. Workforce Certification Assessment Center (build out floor): 25,000 sf
  3. Multiple bond funded renovations: 55,000 sf

Phase 2: July 2016 - June 2018

  1. New Instructional Arts Building: 40,000 sf
  2. Increase surface parking: 170 spaces

Phase 3: Jan 2018 - Dec 2019

  1. Multiple facility condition assessment project