× LoneStarCollegeALERT:

Visit LoneStarCollegeAlert for more information.

2014 Bond Updates

February 2017

LSC-CyFair

  • Instruction and Student Life Building: Exterior masonry work is in progress. Interior drywall is complete. Interior finishes are in progress and permanent power is near
    completion. Overall project construction is expected to be complete in April 2017.

LSC-CyFair Instruction and Student Life Building

  • Cypress Center Workforce Expansion: Demolition is complete. Construction of underground utilities and piers are complete. Slab on grade is still on track for the
    first week in February. This project is still on track to be complete in June 2017.
  • Westway Park Technology Center: The CMAR contract will be presented for consideration of approval at the March 2017 Board of Trustees meeting. Construction is expected to be complete during Spring 2018.

LSC-Kingwood

  • Student Services Center Expansion: Roofing is complete. All framing and MEP rough in is in progress. Construction is expected to be complete in March 2017.

 LSC-Kingwood Student Services Center Expansion

  • Process Technology Center: Structural steel erection, site utilities, and site paving are in progress. Construction is expected to be complete in August 2017.

LSC-Montgomery

  • Conroe Satellite Center: Construction is substantially complete. Installation of owner furnished equipment is underway. Punch list items are being addressed and final preparations for the Grand Opening Event on January 19, 2017 are being completed.
  • Live Entertainment Technology Building Expansion: Steel erection and exterior weather proofing is complete. Masonry has begun. Installation of interior utilities and stud walls are underway. Construction is expected to be complete in March 2017.  

 LSC-Montgomery Live Entertainment Technology Building

LSC-North Harris

  • Construction & Skilled Trades Technology Center: Structural steel and roof decking is complete, and the exterior wall framing, and MEP wall and overhead rough in are in progress. Construction is expected to be complete in July 2017.  

 LSC-North Harris Construction & Skilled Trades Technology Center

  •  East Aldine Satellite Center: It is anticipated that the GMP will be presented for consideration of approval at the April 2017 Board of Trustees meeting. Construction is expected to be complete in May 2018.
  • Relocate Electrical Service Underground: Electrical underground conduit is underway. Construction is expected to be complete in April 2017.
  • Central Plant Renovations: The GMP contract is waiting on LSC execution. Construction is expected to be complete in mid-2017.

LSC-Tomball

  • Health Science Building 3rd Floor Buildout: The project has been completed and an open house was conducted on January 12.

LSC-Tomball Health Science Building

  • South Entrance Drive: Bids have been received and evaluated. It is anticipated that the project will be presented for consideration of approval at the March Board of Trustees meeting.

LSC-University Park

  • Science and Innovation Building: The building is enclosed. Development of interior utilities and partitioning continue. Specialty equipment is arriving and being integrated into the construction. This project is expected to be complete in May 2017.
  • Building 12 & 13 Entrance Canopy and Parking: The work site has been cleared and layout is underway for the underground utilities.

LSC-System-wide Security Updates

  • Satellite Center mass communication upgrades are complete. Security and mass notification upgrades at main campuses will be bid and contracted in two phases. The bid has been put on hold until further notice.

December 2016

LSC-CyFair

  • Cypress Center Workforce Expansion: Construction will begin in December and is expected to be complete in June 2017.
  • Westway Park Technology Center: The GMP is being presented for consideration of approval at the December 2016 Board of Trustees meeting. Construction is expected to be complete in summer 2017.

LSC-Kingwood

  • Student Services Center Expansion: Structural steel erection is complete; roofing is in progress. Construction is expected to be complete in February 2017.
  • Process Technology Center: Foundation, underground site utilities, and site paving are in progress. Construction is expected to be complete in August 2017.

LSC-Montgomery

  • Conroe Satellite Center: Commissioning and utility connections for equipment are in progress. Construction is expected to be complete in January 2017.
  • Live Entertainment Technology Building: Building slab is complete; metal building erection is in progress. Construction is expected to be complete in March 2017.

LSC-North Harris

  • Construction & Skilled Trades Technology Center: Site utilities and paving are complete. Structural steel, roof decking, exterior wall framing, and interior piping are in progress. Construction is expected to be complete in July 2017.
  • East Aldine Satellite Center: It is anticipated that the GMP will be presented for consideration of approval at the April 2017 Board of Trustees meeting. Construction is expected to be complete in May 2018.
  • Relocate Electrical Service Underground: The Contractor is mobilizing. Construction is expected to be complete in April 2017.
  • Central Plant Renovations: The GMP contract is being presented for consideration of approval at the December 2016 Board of Trustees meeting. Construction is expected to be complete in May 2017.

LSC-Tomball

  • Health Science Building - 3rd Floor Buildout: Buildout of Surgical Tech area is expected to be complete in December 2016.
  • South Entrance Drive: Bids have been received and are being evaluated. It is anticipated that the project will be presented for consideration of approval at the February 2017 Board of Trustees meeting. Construction is expected to be complete in fall 2017.

LSC-University Park

  • Science and Innovation Building: Roofing and exterior sheathing are complete. Erection of the front glass curtainwall, interior overhead MEP work, and partition framing are in progress. Construction is expected to be complete in May 2017.

  • Building 12 & 13 Entrance Canopy and Parking: Construction will begin in December and is scheduled for an April 2017 completion.

LSC-System-wide Security Updates

  • Satellite Center mass communication upgrades are complete. Security and mass notification upgrades at main campuses will be bid and contracted in two phases. They will be presented for consideration of approval at the February and March 2017 Board of Trustees meetings, with a fall 2017 completion.

November 2016

LSC-CyFair

  •  Instruction and Student Life Building: The roofing, exterior sheathing, windows, and mechanical/electrical/plumbing rough-ins are complete. Glass curtain wall, brick, and interior drywall are in progress. Overall project construction is expected to be complete in March 2017.

  • Cypress Center Satellite Expansion: Construction will begin in December and is expected to be complete in summer 2017.
  • Westway Park Technology Center: The GMP will be presented for consideration of approval at the December 2016 Board of Trustees meeting. Construction is expected to be complete in summer 2017.

LSC-Kingwood

  • Student Services Center Expansion: Structural steel is in progress. Construction is expected to be complete in February 2017.
  • Process Technology Center: Foundation work is in progress. Construction is expected to be complete in August 2017.

LSC-Montgomery

  • Conroe Satellite Center: Mechanical and electrical equipment, as well as stairs and sidewalks, are complete. Interior walls are complete and finish work is in progress. Construction is expected to be complete in January 2017.
  • Live Entertainment Technology Building: Underground utility installation nearing completion. The building slab will be placed in early November. Construction is expected to be complete in March 2017.

LSC-North Harris

  • Construction & Skilled Trades Technology Center: Foundation and detention pond are complete, while building slab and site utilities are in progress. Construction is expected to be complete in July 2017.
  • East Aldine Satellite Center: The construction documents have been completed and negotiations with Aldine ISD on the associated Interlocal Agreement are in progress.
  • Relocate Electrical Service Underground: The GMP is being presented for consideration of approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in April 2017.
  • Central Plant Renovations: Bidding is in progress. It is anticipated that the GMP will be presented for approval at the December 2016 Board of Trustees meeting. Construction is expected to be complete in May 2017.

LSC-Tomball

  • Health Science Building - 3rd Floor Buildout: Surgical equipment is being installed on the second floor, with completion anticipated in November 2016.
  • South Entrance Drive: Bidding is in progress. It is anticipated that the GMP will be presented for consideration of approval at the February 2017 Board of Trustees meeting, with a fall 2017 construction completion.

LSC-University Park

  • Science and Innovation Building: Steel erection and floor slabs are complete. Roofing, exterior walls, and mechanical, electrical, and plumbing work are in progress. Construction is expected to be complete in May 2017.
  • Building 12 & 13 Entrance Canopy and Parking: Construction will begin in November and is scheduled for a March 2017 completion.

October 2016

LSC-CyFair

  • Instruction and Student Life Building: The roof deck is complete, and the exterior wall and glass are in progress. Overall project construction is expected to be complete in March 2017.
  • Westway Park Technology Center: Subcontractor bidding is in progress. It is anticipated that the GMP will be presented for consideration of approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in July 2017.

LSC-Kingwood

  • Student Services Center Expansion: Foundation work is in progress. Construction is expected to be complete in January 2017.
  • Process Technology Center: Tree removal and site clearing is in progress. The groundbreaking ceremony was held October 4, 2016. Construction is expected to be complete in August 2017.

LSC-Montgomery

  • Conroe Satellite Center: Roofing and brick installation is nearing completion. Utility installation and interior construction are in progress. Construction is expected to be complete in January 2017.
  • Live Entertainment Technology Building: Existing utility surveying is complete, and the building pad is in progress. Construction is expected to be complete in March 2017.

LSC-North Harris

  • Applied Technology Workforce Building: Foundation and building slab are in progress. Construction is expected to be complete in July 2017.
  • East Aldine Satellite Center: Construction documents are complete and it is anticipated that the GMP will be presented for consideration of approval at the February 2017 Board of Trustees meeting. Construction is expected to be complete in March 2018.
  • Relocate Electrical Service Underground: Construction documents are being bid and the permit has been received. It is anticipated that the GMP will be presented for approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in April 2017.

LSC-Tomball

  • Health Science Building - 3rd Floor Buildout: Third floor construction is complete. Associated work on second floor is in progress and is expected to be complete in November 2016.

LSC-University Park

  • Science and Innovation Center: Steel erection is nearing completion. Construction is expected to be complete in May 2017.

September 2016

LSC-CyFair

  • Instruction and Student Life Building: HVAC duct installation is nearing completion and the exterior wall and roof deck are in progress. CASA renovations and south parking lot were complete for the start of the fall semester. Overall project construction is expected to be complete in March 2017.
  • Westway Park Technology Center: Construction documents are complete. It is anticipated that the GMP will be presented for consideration of approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in July 2017. 

LSC-Kingwood

  • Student Services Center Expansion: Earthwork and building pad are complete. Construction is expected to be complete in January 2017.
  • Process Technology Center: Site clearing is in progress. Construction is expected to be complete in August 2017.

LSC-Montgomery

  • Conroe Satellite Center: Exterior walls are complete. Roofing and interior construction are in progress. Construction is expected to be complete in January 2017.
  • Live Entertainment Technology Building: Site clearing is complete. Earthwork is in progress. Construction is expected to be complete in March 2017.
  • Magnolia Satellite Center: Site purchase is being negotiated.

LSC-North Harris

  • Applied Technology Workforce Building: Sitework has begun. Construction is expected to be complete in July 2017.
  • East Aldine Satellite Center: Construction documents are complete. It is anticipated that the GMP will be presented for consideration of approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in December 2017.
  • Transportation and Logistics Institute: Site purchase is being negotiated.
  • Relocate Electrical Service Underground: Construction documents are in progress and it is anticipated that the GMP will be presented for approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in March 2017.

LSC-Tomball

  • Health Science Building - 3rd Floor Buildout: Construction was complete for the start of the fall semester.

LSC-University Park

  • Science and Innovation Center: Steel erection is in progress. Construction is expected to be complete in May 2017.

August 2016

LSC-CyFair

  •  Instruction and Student Life Building: Building slab and second floor have been placed and structural steel erection is complete. Masonry walls on Central Plant are complete. Construction continues on schedule and is expected to be complete in March 2017.
  • Cypress Center Workforce Expansion: Construction is scheduled to begin in November 2016 simultaneous with the Westway Park Technology Center and be complete in May 2017.
  • Westway Park Technology Center: Construction documents are in progress. It is anticipated that the GMP will be presented for consideration of approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in July 2017.

LSC-Kingwood

  • Student Services Center Expansion: Earthwork and building pad construction are in progress.
  • Process Technology Center: The GMP was approved at the June 2016 Board of Trustees meeting and the contract is being finalized.

LSC-Montgomery

  • Conroe Satellite Center: Building foundation is complete and exterior walls are in progress. Construction is expected to be complete in January 2017.
  • Live Entertainment Technology Building: The GMP was approved at the June 2016 Board of Trustees meeting and the Contractor has mobilized. Construction is expected to be complete in March 2017.
  • Magnolia Satellite Center: Site alternatives continue to be evaluated.

LSC-North Harris

  • Construction & Skilled Trades Technology Center: The GMP was approved at the June 2016 Board of Trustees meeting. Construction is expected to be complete in July 2017.
  • East Aldine Satellite Center: The Aldine ISD Early College Facility Design Development documents are in progress and it is anticipated that the GMP will be presented for consideration of approval at the November 2016 Board of Trustees meeting. Construction of both projects is expected to be complete in November 2017.
  • Transportation and Logistics Institute: Site purchase alternatives continue to be evaluated.
  • Relocate Electrical Service Underground: Design Development is in progress and it is anticipated that the GMP will be presented for approval at the November 2016 Board of Trustees meeting. Construction is expected to be complete in March 2017.

LSC-Tomball

  • Health Science Building - 3rd Floor Buildout: Construction is progressing on schedule and is expected to be complete in August 2016.

LSC-University Park

  • Science and Innovation Center: Building slab is nearing completion. Construction is expected to be complete in May 2017.
  • Classroom Renovations in Building 12, Level 7: Construction is progressing on schedule and is expected to be complete in August 2016.

June 2016

LSC-CyFair

  • Instruction and Student Life Building: Building slab has been placed and structural steel erection is in progress. Masonry walls on Central Plant are in progress. Construction is expected to be complete in March 2017.
  • Cypress Center Workforce Expansion: The Guaranteed Maximum Price (“GMP”) is being presented for consideration of approval at the June 2016 Board of Trustees meeting. Construction is expected to be complete in March 2017.
  • Westway Park Technology Center: Construction documents are in progress. It is anticipated that the GMP will be presented for consideration of approval at the September 2016 Board of Trustees meeting. Construction is expected to be complete in May 2017.

LSC-Kingwood

  • Student Services Center Expansion: Site utilities are in progress. Construction is expected to be complete in January 2017.
  • Process Technology Center: The GMP is being presented for consideration of approval at the June 2016 Board of Trustees meeting. Construction is expected to be complete in July 2017.

LSC-Montgomery

  • Conroe Satellite Center: Building foundation is in progress. Construction is expected to be complete in January 2017.
  • Live Entertainment Technology Building: The GMP is being presented for consideration of approval at the June 2016 Board of Trustees meeting. Construction is expected to be complete
    in March 2017.
  • Magnolia Satellite Center: Negotiations on a potential land tract are underway.

LSC-North Harris

  • Construction and Skilled Trades Technology Center: The GMP is being presented for approval at the June 2016 Board of Trustees meeting. Construction is expected to be complete in June 2017.
  • East Aldine Satellite Center: The Aldine ISD Early College Facility Design Development documents are in progress and it is anticipated that the GMP will be presented for consideration of approval at the October 2016 Board of Trustees meeting. Construction of both projects is expected to be complete in November 2017.
  • Transportation and Logistics Institute: Negotiations on a potential land tract are underway.
  • Relocate Electrical Service Underground: Design Development documents are in progress and it is anticipated that the GMP will be presented for approval at the September 2016 Board of Trustees meeting. Construction is expected to be complete in January 2017.

LSC-Tomball

  • Health Science Building - 3rd Floor Build out: Interior partitions and mechanical, electrical, and plumbing overhead work in progress. Construction is expected to be complete in August 2016.

LSC-University Park

  • Science and Innovation Center: Underground utility installation is in progress. Construction is expected to be complete in May 2017.
  • Workforce Assessment Center: Construction documents are in progress. It is anticipated that the GMP will be presented for consideration of approval at the September 2016 Board of Trustees meeting. Construction of this interior renovation project is expected to be complete in December 2016.

 

May 2016

LSC-CyFair

 

Construction continues on the new Instructional/Student Life building at Lone Star College-CyFair. Constructed on 15 acres, the new building will not only house new faculty and dean suites, but instructional and student spaces, 750 parking spaces for students and staff and a three-level Learning Garden.

 

April 2016

LSC-University Park

 

 

The groundbreaking for LSC-University Park’s new Center for Science & Innovation begins at 10 a.m. on Thursday, April 28, near the intersection of University Park Campus Drive and Compaq Center Drive West.

This innovative facility will provide students with a state-of-the-art learning environment and will encourage more students to consider STEM careers.
Designed by Kirksey Architecture, the three-story structure will have 12 science labs for chemistry and biology, an “innovation space” with a tutoring area and a sprawling geology teaching wall. In addition, students and visitors alike can view celestial objects through a variety of telescopes from the observation deck atop the Center of Science & Innovation.

LSC-University Park President Shah Ardalan said the 50,000-square-foot building, due to open in Fall 2017, will help the College meet the academic needs of its rapidly growing population.

 

March 2016

LSC-CyFair

 

 

LSC-CyFair broke ground on its new instructional building March 7. The 75,000 square foot facility will be built between the center for academic affairs and student affairs building and house 16 classrooms, 3 multipurpose class rooms, 4 computer classrooms, 2 prototype computer classroom and 1 open computer lab.

The building is expected to open in spring 2017 and feature a 3 level landscaped outdoor space, known as the learning garden.

 

February 2016

 

LSC-University Park

 

LSC-University Park plans to break ground on its new 50,000 square foot science building in March 2016. The LSCS Board of Trustees approved the pending design during its February 2016 meeting.

The three-story building will house 12 science labs and be equipped with the latest technology and is expected to be completed for the start of fall 2017 classes.

 

LSC-CyFair

 

The LSC-Westway Park Technology Center location has been finalized. The center will be at 5060 Westway Park Boulevard. LSC will initially build out 50,000 square foot of the 130,000 square foot facility which is expected to open late spring 2017.

 

January 2016

 

LSC-Kingwood

The design development of the LSC-Process Technology Center has been completed. The 50,000 square foot center is located on 8.3 acres in Generation Park on Lockwood Drive across from Summer Creek High School. The facility is slated to open in fall 2017. Until that time, LSC-Kingwood will start the Process Technology Associate of Applied Science degree in January 2017 at the LSC-Atascocita Center.