2014 Bond LSC-CyFair
We are currently updating the GO Bond Projects web pages. More information will be available and the web pages updated soon.
Campus Details
- 228 acres
- 663,000 sf
- 3,900 parking spaces
Project Plans
LSC-CyFair Project Phasing
Phase 1: Feb 2015 - Dec 2016
- New Instructional Building: 75,000 sf
- Central Plant Expansion: 3,000 sf
- Increase surface parking by 750 spaces
- Renovations: Appx 10,000 sf
- LSC-Westway Park Technology Center: 50,000 sf (Spring 2017)
Cypress Center Workforce Expansion: 5,000 sf
(Satellite location; expand existing building)
Phase 2: July 2016 - June 2018
- Renovations: 23,000 sf
- Multiple facility condition assesment projects
Phase 3: Jan 2018 - Dec 2019
No plans at this time.