2014 Bond LSC-CyFair

We are currently updating the GO Bond Projects web pages. More information will be available and the web pages updated soon.

Campus Details

  • 228 acres
  • 663,000 sf
  • 3,900 parking spaces

Project Plans

LSC-CyFair Project Phasing

Phase 1: Feb 2015 - Dec 2016

  1. New Instructional Building: 75,000 sf
  2. Central Plant Expansion: 3,000 sf
  3. Increase surface parking by 750 spaces
  4. Renovations: Appx 10,000 sf
  5. LSC-Westway Park Technology Center: 50,000 sf (Spring 2017)
    Cypress Center Workforce Expansion: 5,000 sf
    (Satellite location; expand existing building)

Phase 2: July 2016 - June 2018

  1. Renovations: 23,000 sf
  2. Multiple facility condition assesment projects

Phase 3: Jan 2018 - Dec 2019

No plans at this time.