![]() |
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. The contractor is Landscape Art and
the construction notice to proceed was issued August 2020. Substantial Completion: Spring 2021 Budget: $2,650,000
LSC-Corporate College: Transportation & Global Logistics Traning Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction was completed May 4, 2020. Phase II, Hardy Access Road began construction November 2020. Substantial Completion: Spring 2021 Budget: $13,000,000
LSC-University Park: Visual Performing Arts Center: A new 30,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech. Schematic Design was completed October 15, 2020. Substantial Completion: Fall 2022 Budget: $21,675,000
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg. The construction firm is Durotech, Inc. General Contractors and construction notice to proceed was issued August 24, 2020. Substantial Completion: Fall 2021 Budget: $25,650,000
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and construction notice to proceed was issued June 15, 2020. Substantial Completion: Fall 2021 Budget: $27,590,000
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was
completed July 2019. Substantial Completion: TBD Budget: $28,858,538
![]() |
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. The contractor is Landscape Art and the construction notice to proceed was issued August 2020. Substantial Completion: Spring 2021 Budget: $2,650,000.
LSC-Corporate College: Transportation and Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction was completed May 4, 2020. Phase II, Hardy Access Road began construction November 2020. Substantial Completion: Spring 2021 Budget: $13,000,000.
LSC-University Park: Visual Performing Arts Center: A new 30,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech. Schematic Design was completed October 15, 2020. Substantial Completion: Fall 2022 Budget: $21,675,000.
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg. The construction firm is Durotech, Inc. General Contractors and construction notice to proceed was issued August 24, 2020. Substantial Completion: Fall 2021 Budget: $25,650,000.
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and construction notice to proceed
was issued June 15, 2020. Substantial Completion: Fall 2021 Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538.
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: November 18, 2020.
![]() |
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. The contractor is Landscape Art and the construction notice to proceed was issued August 2020. Substantial Completion: Fall 2020 Budget: $2,650,000
LSC-Corporate College: Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction was completed May 4, 2020. Phase II, Hardy Access Road began construction November 2020. Substantial Completion: Spring 2021 Budget: $13,000,000
LSC-University Park: Visual Performing Arts Center: A new 30,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech. Schematic Design was completed October 15, 2020. Substantial Completion: Fall 2022 Budget: $21,675,000
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg. The construction firm is Durotech, Inc. General Contractors and construction notice to proceed was issued August 24, 2020. Substantial Completion: Fall 2021 Budget: $25,650,000
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and construction notice to proceed was issued June 15, 2020. Substantial Completion: Fall 2021 Budget: $27,590,000
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: November 18, 2020
![]() |
LSC-Kingwood: Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Project completion was reached on October 30, 2020. Substantial Completion: Fall 2020 (COVID-19 delay)
Budget: $52,553,603
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. The contractor is Landscape Art and the construction notice to proceed was issued August 2020. Substantial Completion: Fall 2020 Budget: $2,650,000
LSC-Corporate College: Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: May 4, 2020 Budget: $13,000,000
LSC-University Park: Visual Performing Arts Center: A new 30,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin Spring 2020. Substantial Completion: Fall 2022 Budget: $21,675,000
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021 Budget: $25,650,000
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is Spring 2020. Substantial Completion: Fall 2021 Budget: $27,590,000
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: Fall 2020
![]() |
LSC-Kingwood: Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by Spring 2020. Substantial Completion: Summer 2020 (COVID-19 delay) Budget: $52,553,603
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. The contractor is Landscape Art and the construction notice to proceed was issued August 2020. Substantial Completion: Fall 2020 Budget: $2,650,000
LSC-Corporate College: Transportation & Global Logistices Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: May 4, 2020 Budget: $13,000,000
LSC-University Park: Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin Spring 2020. Substantial Completion: Fall 2022 Budget: $21,675,000
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021 Budget: $25,650,000
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is Spring 2020. Substantial Completion: Fall 2021 Budget: $27,590,000
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and
programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse
to support the needs of the Fallbrook community. Substantial Completion: Fall 2020
![]() |
LSC-Kingwood: Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by Spring 2020. Substantial Completion: Summer 2020 (COVID-19 delay) Budget: $52,553,603.
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Contractor negotiations are in process. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Corporate College: Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: May 4, 2020 Budget: $13,000,000.
LSC-University Park: Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin Spring 2020. Substantial Completion: Fall 2022 Budget: $21,675,000.
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities.The architect is Harrison Kornberg and programming began June 2018. The construction
firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021 Budget: $25,650,000.
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice
to proceed is Spring 2020. Substantial Completion: Fall 2021 Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538.
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: Fall 2020.
![]() |
We are currently updating the GO Bond Projects web pages. More information will be available and the web pages updated soon.
LSC-Kingwood: Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by Spring 2020. Substantial Completion: Summer 2020 (COVID-19 delay) Budget: $52,553,603.
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Contractor negotiations are in process. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Corporate College: Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: May 4, 2020. Budget: $13,000,000.
LSC-University Park: Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin Spring 2020. Substantial Completion: Fall 2022. Budget: $21,675,000.
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021. Budget: $25,650,000.
LSC-Kingwood: Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is Spring 2020. Substantial Completion: Fall 2021. Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD. Budget: $28,858,538.
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: Fall 2020.
![]() |
LSC-Kingwood: Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by Spring 2020. Substantial Completion: Spring 2019 (delay COVID-19) Budget: $52,553,603.
LSC-Tomball: South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new LSC-Tomball South Drive Entrance completed January 2018. Contractor negotiations are in
process. Substantial Completion: Fall 2020. Budget: $2,650,000.
LSC-Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin Spring 2020.
Substantial Completion: Fall 2022. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021. Budget: $25,650,000.
Health Professions Center: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is Spring 2020. Substantial Completion: Fall 2021. Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and
programming was completed July 2019. Substantial Completion: TBD. Budget: $28,858,538.
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse
to support the needs of the Fallbrook community. Substantial Completion: Fall 2020.
Land Purchase: A new land purchase of 211.23 acres has been placed under contract, and Due Diligence inspections are to begin. Effective Date: February 2020. Value: $13,500,000.
|
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by Spring 2020. Substantial Completion: Spring 2019. Budget: $52,553,603.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new LSC-Tomball South Drive Entrance completed January 2018. Contractor negotiations are in process. ? Substantial Completion: Fall 2020. Budget: $2,650,000.
LSC-Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction
firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin Spring 2020. Substantial Completion: Fall 2022.? Budget: $21,675,000.
tudent Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021. Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is Spring 2020. Substantial Completion: Fall 2021. Budget: $27,590,000.
A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD. Budget: $28,858,538.
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: Fall 2020.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by February 2020. Substantial Completion: Spring 2019. Budget: $52,553,603.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Contractor negotiations are in process. Substantial Completion: Fall 2020. Budget: $2,650,000.
LSC-Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The Construction Manager at Risk is Durotech with re-programming to begin February 2020. Substantial Completion: Fall 2022. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors.Substantial Completion: Fall 2021. Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is February 2020.Substantial Completion: Fall 2021. Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD. Budget: $28,858,538.
LSC-Houston North Fallbrook: A new 55,000+ sf building, this building will have two stories with 14 classrooms, two computer labs, two science labs, and a 4,000 sf logistics management warehouse to support the needs of the Fallbrook community. Substantial Completion: Fall 2020.
LSC-Drilling Services Training Center: A lease agreement was finalized with Technip FMC for one year for use of the building at the LSC-Corporate College Drilling Services Training Center. Effective Date: December 2019. Value: $51,000 in revenue.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by February 2020. Substantial Completion: Spring 2019. Budget: $52,553,603.
South Entrance Drive Monument:A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Currently in bid process for the project. Substantial Completion: Fall 2020. Budget: $2,650,000.
LSC-Transportation & Global Logistics Technology Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction
firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. Currently selecting the Construction Manager at Risk with re-programming to begin December 2019. Substantial Completion: Fall 2022. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities.The architect is Harrison Kornberg and programming began June 2018. The construction
firm is Durotech, Inc. General Contractors. Substantial Completion: Fall 2021. Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice
to proceed is February 2020. Substantial Completion: Fall 2021. Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD. Budget: $28,858,538.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway and expected to be complete by February 2020. Substantial Completion: Spring 2019 Budget: $52,553,603.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Currently in bid process for the project. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Transportation & Logistics Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020 Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. Currently selecting the Construction Manager at Risk with re-programming to begin December 2019. Substantial Completion: Spring 2022 Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors.
Substantial Completion: Spring 2021 Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch. The construction firm is Tellepsen and estimated construction notice to proceed is February 2020. Substantial Completion: Fall 2021 Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538.
![]() |
LSC-Kingwood: Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway as of May 2019 and are expected to be complete by September 2019. Substantial Completion: Spring 2019 Budget: $52,553,603.
LSC-University Park: Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects. The construction firm is Gadberry. Substantial Completion: Summer 2019 Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group. The construction firm is Bartlett Cocke General Contractors. The project met substantial completion on July 19, 2019.Substantial Completion: Summer 2019 Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Survey approved with TxDOT to purchase property. Appraisals being prepared.Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Transportation & Logistics Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020 Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Spring 2022 Budget: $21,675,000.
LSC-Montgomery: Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Spring 2021 Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and we are now in schematic design. The construction firm is Tellepsen.Substantial Completion: Fall 2021 Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: TBD Budget: $28,858,538.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library, respectively. Final completion details are underway as of May 2019 and are expected to be complete by September 2019. Substantial Completion: Spring 2019 Budget: $48,981,935.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects. The construction firm is Gadberry. Substantial Completion: Summer 2019 Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group. The construction firm is Bartlett Cocke General Contractors. The project met substantial completion on July 19, 2019. Substantial Completion: Summer 2019 Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Survey approved with TxDOT to purchase property. Appraisals being prepared. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Transportation and Logistics Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020 Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Spring 2022 Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors.
Substantial Completion: Spring 2021 Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and we are now in schematic design. The construction firm is Tellepsen. Substantial Completion: Fall 2021
Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming was completed July 2019. Substantial Completion: Spring 2022 Budget: $28,858,538.
|
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant. Substantial completion was reached on January 6, 2019 for five of the six buildings as well as May 17, 2019 for the library. Final completion details are underway as of May 2019 and are expected to be complete by September 2019.Substantial Completion: Spring 2019 Budget: $48,981,935.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is Gadberry and they began construction February 2019.Substantial Completion: Summer 2019 Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December 2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019 Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Survey approved with TxDOT to purchase property. Appraisals being prepared. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Transportation and Logistics Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020 Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Spring 2022 Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Spring 2021 Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and we are now in schematic design. The construction firm is Tellepsen. Substantial Completion: Fall 2021 Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming is beginning April 2019. Substantial Completion: Spring 2022
Budget: $28,858,538.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings has reached substantial construction firm is Anslow Bryant and construction began July 2018. Classes resumed in the five completed buildings for Spring 2019 with the Library building scheduled for completion and opening in May 2019. Substantial Completion: Spring 2019 Budget: $48,981,935.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is Gadberry and they began construction February 2019. Substantial Completion: Summer 2019 Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December 2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019 Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Survey approved with TxDOT to purchase property. Appraisals being prepared. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Transportation and Logistics Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020 Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Spring 2022 Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors.
Substantial Completion: Spring 2021 Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and schematic design began July 2018. The construction firm is Tellepsen. Substantial Completion: Fall 2021
Budget: $27,590,000.
LSC-Magnolia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming is beginning April 2019. Substantial Completion: Spring 2022
Budget: $28,858,538.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings has reached substantial completion. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant and construction began July 2018. Classes resumed in the
five completed buildings for Spring 2019 with the Library building scheduled for completion and opening in May 2019. Substantial Completion: Spring 2019. Budget: $49,871,800.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is Gadberry and they began construction February 2019.Substantial Completion: Summer 2019.Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December
2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019. Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Survey approved with TxDOT to purchase property. Appraisals being prepared. Substantial Completion: Fall 2020 Budget: $2,650,000.
LSC-Transportation and Logistics Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction
firm is Tellepsen and construction began February 2019. Substantial Completion: Spring 2020. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Spring 2022. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Spring 2021. Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and schematic design began July 2018. The construction firm is Tellepsen. Substantial Completion: Fall 2021. Budget: $27,590,000.
LSC-Magnonlia Center: A new 50,000+ sf building, this project will support the needs of the Magnolia community. Land was recently purchased, the architect is Harrison Kornberg and programming is beginning April 2019. Substantial Completion: Spring 2022. Budget: $28,858,538.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings has reached substantial completion. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant and construction began July 2018. Classes resumed in the five completed buildings for Spring 2019 with the Library building scheduled for completionand opening in April 2019. Substantial Completion: Spring 2019. Budget: $45,000,000.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is Gadberry and they began construction February 2019.Substantial Completion: Summer 2019.Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December 2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019. Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Discussions and a survey are in progress with TxDOT to purchase property as well as appraisals being prepared.Substantial Completion: Fall 2019. Budget: $2,650,000.
LSC-Transportation & Logistics Center: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Late Fall 2019. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Summer 2021. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Spring 2021. Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and schematic design began July 2018. The construction firm is Tellepsen. Substantial Completion: Spring 2021. Budget: $27,590,000.
![]() |
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings has reached substantial completion. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant and construction began July 2018. Classes resumed in the five completed buildings for Spring 2019 with the Library building scheduled for completion and opening in April 2019. Substantial Completion: Spring 2019. Budget: $45,000,000.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is Gadberry and they began construction February 2019.
Substantial Completion: Summer 2019. Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December 2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019. Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Discussions and a survey are in progress with TxDOT to purchase property as well as appraisals being prepared.
Substantial Completion: Fall 2019. Budget: $2,650,000.
Transportation Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction began February 2019. Substantial Completion: Late Fall 2019.
Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Summer 2021. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Spring 2021.
Budget: $25,650,000.
Healthcare Instructional Building: A new 50,000+ sf building, this project will support a healthcare instructional program. The architect is AutoArch and schematic design began July 2018. The construction firm is Tellepsen. Substantial Completion: Spring 2021. Budget: $27,590,000.
![]()
|
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of five of six buildings has reached substantial completion. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant and construction began July 2018. Classes resumed in the five completed buildings for Spring 2019 with the Library building scheduled for completion and opening in March 2019. Substantial Completion: Spring 2019. Budget: $53,813,494.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is pending execution of contract for construction to begin February 2019. Substantial Completion: Summer 2019. Budget: $840,000.
East Aldine Satellite Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December 2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019. Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Discussions and a survey are in progress with TxDOT to purchase property. Substantial Completion: Fall 2019. Budget: $2,650,000.
Transportation Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction is estimated to begin January 2019. Substantial Completion: Fall 2019. Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Summer 2021. Budget: $21,675,000.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Spring 2021. Budget: $25,650,000.
Healthcare Instructional Building: A new 60,000 sf building, this project will support a healthcare instructional program. The architect is AutoArch and schematic design began July 2018. The construction firm is Tellepsen. Substantial Completion: Spring 2021. Budget: $27,590,000.
![]() |
LSC-Westway Park Technology Center: A renovation of a 54,000 sf building, this project will support technology programs such as information systems and related support. The architect is BRW Architects and design was completed December 2017. The construction firm is Brookstone, L.P. and construction began April 2018. Substantial Completion: December 2018 Budget: $27,450,000.
Hurricane Harvey Recovery: A renovation of 200,000 sf of the first floors of six buildings, this project will support the recovery of the main campus operations. The architect is AutoArch and design was completed August 2018. The construction firm is Anslow Bryant and construction began July 2018. For temporary accommodations, an elevator rebuild, other minor repairs required for access to level two classrooms in the Administration and Library buildings, and modular classrooms are complete and being utilized for Summer and Fall 2018 classes. Substantial Completion: December 2018 Budget: $53,813,494.
Student Life Renovation: A renovation of 9,583 sf in the Commons Building Level 2, this project will support student life for the college. The architect is RdlR Architects and design was completed November 2017. The construction firm is pending execution of contract for construction to begin November 2018. Substantial Completion: Summer 2019 Budget: $840,000.
LSC-East Aldine Center: A new 65,000 sf building, this project will support general curriculum studies and workforce instruction in the Aldine School District area; as well as an Early College program partnership with Aldine ISD. The architect is Texas IBI Group and design was completed December 2017. The construction firm is Bartlett Cocke General Contractors and construction began March 2018. Substantial Completion: Summer 2019 Budget: $28,940,000.
South Entrance Drive Monument: A new main entrance monument, sign, and landscaping, this project will support the new Tomball South Drive Entrance completed January 2018. Discussions and a survey are in progress with TxDOT to purchase property. Substantial Completion: Fall 2019 Budget: $2,650,000.
Transportation Institute: A new 16,000 sf building, this project will support the growing truck driving program. The architect is PBK Architects and design was completed September 2018. The construction firm is Tellepsen and construction is estimated to begin January 2019. Substantial Completion: Fall 2019 Budget: $13,000,000.
Visual Performing Arts Center: A new 40,000 sf building, this project will support an instructional arts program. The architect is Studio Red Architects and programming began May 2018. Substantial Completion: Summer 2020 Budget: $21,675,00.
Student Services Building: A new 50,000+ sf building, this project will support expanded student services capabilities. The architect is Harrison Kornberg and programming began June 2018. The construction firm is Durotech, Inc. General Contractors. Substantial Completion: Summer 2020 Budget: $25,650,000.
Healthcare Instructional Building: A new 60,000 sf building, this project will support a healthcare instructional program. The architect is AutoArch and schematic design began July 2018. The construction firm is Tellepsen and construction is estimated to begin May 2019. Substantial Completion: Summer 2020 Budget: $27,590,000.
LSC-Kingwood Main Campus: CMAR contract for build back has been awarded to Anslow Bryant. Design has started for the build back construction for six buildings. Elevator rebuild and other minor repairs required for access to level two (L2) classrooms in the Administration and Library buildings are complete. Utility design for Modular Classroom buildings are complete and scheduled for installation Summer 2018.
![]() |
LSC-Process Technology Center |
![]() |
LSC-University Park Science and Innovation Building -- Photo courtesy JLL |
Center for Academic and Student Affairs -- Photo courtsey JLL |
![]() |
LSC-Process Technology Center -- Photo courtsey JLL |
![]() |
LSC-Montgomery Live Entertainment Technology Building -- photo courtsey of JLL |
![]() |
LSC-Process Technology Center -- Photo courtsey JLL |
![]() |
LSC-Construction & Skilled Trades Technology Center -- Photo courtsey JLL |
![]() |
LSC-CyFair Center for Academic and Student Engagement Building -- Photo courtsey JLL |
![]() |
LSC-Process Technology Center -- Photo courtsey JLL |
![]() |
LSC-North Harris Construction & Skilled Trades Technology Center -- Photo courtesy JLL |
![]() |
LSC-University Park Science and Innovation Building -- Photo courtesy JLL |
![]() |
LSC-Cy Fair Center for Academic and Student Engagement Building -- photo courtesy JLL |
![]() |
LSC-Kingwood Student Services -- photo courtsey JLL |
![]() |
LSC-Process Technology Center -- photo courtsey JLL |
![]() |
LSC-North Harris Construction & Skilled Trades Technology Center -- photo courtsey JLL |
![]() |
LSC-University Park Library Remodel -- photo courtsey JLL |
![]() |
LSC-Cy Fair Center for Academic and Student Engagement Building -- photo courtesy JLL |
![]() |
LSC-Cypress Center -- photo courtsey JLL |
![]() |
LSC-Kingwood Student Services -- photo courtsey JLL |
![]() |
LSC-Process Technology Center -- photo courtesy JLL |
![]() |
LSC-Montgomery Live Entertainment Technology Building -- photo courtsey of JLL |
![]() |
LSC-North Harris Construction & Skilled Trades Technology Center -- photo courtsey of JLL |
![]() |
LSC-East Aldine Center -- photo courtsey of JLL |
![]() |
LSC-University Park Science and Innovation Building -- photo courtsey of JLL |
![]() |
LSC-CyFair Center for Academic and Student Engagement Building -- photo courtesy JLL |
![]() |
LSC-Cypress Center -- photo courtesy JLL |
![]() |
LSC Kingwood Student Services Center -- photo courtesy JLL |
![]() |
LSC-Process Technology Center -- photo courtesy JLL |
![]() |
Science and Innovation Building -- photo courtesy JLL |
![]() |
LSC-CyFair Center for Academic and Student Engagement Building -- photo courtesy JLL |
![]() |
LSC-Kingwood Student Services Center -- photo courtsey JLL |
![]() |
LSC- Montgomery Live Entertainment Technology Building -- photo courtsey JLL |
![]() |
LSC-North Harris Construction & Skilled Trades Technology Center -- photo courtsey JLL |
![]() |
Science and Innovation Building @ LSC-University Park |
|
LSC-CyFair Center for Academic and Student Engagement Building -- photo courtesy JLL |
|
LSC-Kingwood Student Services Center Expansion -- photo courtsey JLL |
|
LSC-Montgomery Live Entertainment Technology Building -- photo courtsey JLL |
|
LSC-North Harris Construction & Skilled Trades Technology Center -- photo courtsey JLL |
|
LSC-Tomball Health Science Building -- photo courtsey JLL |
|
Construction continues on the new Center for Academic and Student Engagement Building at Lone Star College-CyFair. Constructed on 15 acres, the new building will not only house new faculty and dean suites, but instructional and student spaces, 750 parking spaces for students and staff and a three-level Learning Garden. |
![]() |
The groundbreaking for LSC-University Park’s new Center for Science & Innovation begins at 10 a.m. on Thursday, April 28, near the intersection of University Park Campus Drive and Compaq Center Drive West. This innovative facility will provide students with a state-of-the-art learning environment and will encourage more students to consider STEM careers. LSC-University Park President Shah Ardalan said the 50,000-square-foot building, due to open in Fall 2017, will help the College meet the academic needs of its rapidly growing population. |
![]() |
LSC-CyFair broke ground on its new instructional building March 7. The 75,000 square foot facility will be built between the center for academic affairs and student affairs building and house 16 classrooms, 3 multipurpose class rooms, 4 computer classrooms, 2 prototype computer classroom and 1 open computer lab. The building is expected to open in spring 2017 and feature a 3 level landscaped outdoor space, known as the learning garden. |
![]() |
LSC-University Park plans to break ground on its new 50,000 square foot science building in March 2016. The LSCS Board of Trustees approved the pending design during its February 2016 meeting. The three-story building will house 12 science labs and be equipped with the latest technology and is expected to be completed for the start of fall 2017 classes. |
![]() |
The LSC-Westway Park Technology Center location has been finalized. The center will be at 5060 Westway Park Boulevard. LSC will initially build out 50,000 square foot of the 130,000 square foot facility which is expected to open late spring 2017. |
![]() |
The design development of the LSC-Process Technology Center has been completed. The 50,000 square foot center is located on 8.3 acres in Generation Park on Lockwood Drive across from Summer Creek High School. The facility is slated to open in fall 2017. Until that time, LSC-Kingwood will start the Process Technology Associate of Applied Science degree in January 2017 at the LSC-Atascocita Center. |